D
dietmarhannam
I have read many topics about working offline on a project but none
seem to answer the question i have.
I have a desktop machine running Project Pro 2003 which i use to
connect to the server and take offline copies and adjust before
updating Project Server.
I also have a notebook running Project Standard 2003.
Here's the scenario:
- I want to be able take a copy of a project offline (On the desktop)
- Transfer the project file to my notebook to work on out of the office
- Transfer the file back on to the desktop
- Update project server with the changes made to the project.
The problem i have at the moment is i change the project, add it back
to the desktop but when i publish it stores the project as a workgroup
file and not an enterprise file.
Any ideas of the best method? Don't really want to spend an extra £400
on Pro version!
Thanks in anticipation of help,
Dietmar
seem to answer the question i have.
I have a desktop machine running Project Pro 2003 which i use to
connect to the server and take offline copies and adjust before
updating Project Server.
I also have a notebook running Project Standard 2003.
Here's the scenario:
- I want to be able take a copy of a project offline (On the desktop)
- Transfer the project file to my notebook to work on out of the office
- Transfer the file back on to the desktop
- Update project server with the changes made to the project.
The problem i have at the moment is i change the project, add it back
to the desktop but when i publish it stores the project as a workgroup
file and not an enterprise file.
Any ideas of the best method? Don't really want to spend an extra £400
on Pro version!
Thanks in anticipation of help,
Dietmar