N
neil
Hi,
I've been working on a function to calculate how many quarters there
are between two dates - but not the standard business quarters -
effectively what I am trying to work out is the number of complete
three month periods between two dates.
Example:
Start Date: 27/02/2006
End Date: 19/04/2013
I need to calculate how many complete three month periods have passed
between the two dates - this is not as simple as converting the dates
to a timestamp, defining a year as 60 * 60 * 24 * 365.25 seconds, then
dividing by 4, as the length of months do differ, as henceforth
quarters will differ.
[while the above would work in a lot of cases, it would sometimes fall
due to different lengths of months].
i.e. if you adjust the start dates:
Quarter 1: 1 Feb - 30 April - 89 days
Quarter 2: 1 May - 31 July - 92 days
Therefore, I am trying to figure out how many entire three month
periods has passed between the two dates.
I'm sure this is no specific function that will do, but can it be done
with a combination of other existing function - at the moment it looks
like I'm going to have to write a VBA macro to parse the dates using
lots of IF..ELSE statements.
Thanks
Neil.
I've been working on a function to calculate how many quarters there
are between two dates - but not the standard business quarters -
effectively what I am trying to work out is the number of complete
three month periods between two dates.
Example:
Start Date: 27/02/2006
End Date: 19/04/2013
I need to calculate how many complete three month periods have passed
between the two dates - this is not as simple as converting the dates
to a timestamp, defining a year as 60 * 60 * 24 * 365.25 seconds, then
dividing by 4, as the length of months do differ, as henceforth
quarters will differ.
[while the above would work in a lot of cases, it would sometimes fall
due to different lengths of months].
i.e. if you adjust the start dates:
Quarter 1: 1 Feb - 30 April - 89 days
Quarter 2: 1 May - 31 July - 92 days
Therefore, I am trying to figure out how many entire three month
periods has passed between the two dates.
I'm sure this is no specific function that will do, but can it be done
with a combination of other existing function - at the moment it looks
like I'm going to have to write a VBA macro to parse the dates using
lots of IF..ELSE statements.
Thanks
Neil.