This newsgroup has been an imense help for me while setting up a new Project
Server.
I'm running into a problem with changing working times for enterprise
resources. I'm able to change days for individual resources to non-working
time in the Enterprise Resource Pool. However, it seems like I have to close
out of whatever project I'm in at the time and re-open it to get the project
to recognize that the time for that resource cannot be assigned.
Basically, if I change the time to non-working with a project open, it will
allow me to schedule a resource during that non-working time in the project
unless I open and then close it.
This is a serious problem for me, as I want to leave my master project open.
Closing it and re-opening it is a process that takes over an hour and I don't
want to have to do this every time a resource requests a day off. Does anyone
have a solution to this extremely frustrating issue?
Thanks for all the help I've gotten so far just by reading other's posts!
This newsgroup has been an imense help for me while setting up a new Project
Server.
I'm running into a problem with changing working times for enterprise
resources. I'm able to change days for individual resources to non-working
time in the Enterprise Resource Pool. However, it seems like I have to close
out of whatever project I'm in at the time and re-open it to get the project
to recognize that the time for that resource cannot be assigned.
Basically, if I change the time to non-working with a project open, it will
allow me to schedule a resource during that non-working time in the project
unless I open and then close it.
This is a serious problem for me, as I want to leave my master project open.
Closing it and re-opening it is a process that takes over an hour and I don't
want to have to do this every time a resource requests a day off. Does anyone
have a solution to this extremely frustrating issue?