Please help before I tear ALL of my hair out.
I am trying to create a project for an on site installation lasting 6 months.
For 2 weeks of the period, there is a shutdown which I want to highlight on
the Gantt chart in the form of a colour or shape, whatever, anything so that
these two weeks will immediately stand out when the project is pinned up on a
site office wall!
There is work ongoing during the shutdown period so I can't just make it
non-working time. Is there any way I can highlight nondefault working time to
make it stand out?
I am trying to create a project for an on site installation lasting 6 months.
For 2 weeks of the period, there is a shutdown which I want to highlight on
the Gantt chart in the form of a colour or shape, whatever, anything so that
these two weeks will immediately stand out when the project is pinned up on a
site office wall!
There is work ongoing during the shutdown period so I can't just make it
non-working time. Is there any way I can highlight nondefault working time to
make it stand out?