J
Judy Stowell
Working on MS Project Server 2007. Our standard enterprise calendar is set
to a 6-hour workday. We created an Eight Hour Workday calendar for a
particular resource. We set the resource to this calendar and also set the
task he was assigned to to this calendar. The 'Work' column still displays
6 hours for a 1 day duration task however. Is there anything else we can
try?
Thanks,
Judy Stowell
to a 6-hour workday. We created an Eight Hour Workday calendar for a
particular resource. We set the resource to this calendar and also set the
task he was assigned to to this calendar. The 'Work' column still displays
6 hours for a 1 day duration task however. Is there anything else we can
try?
Thanks,
Judy Stowell