Working Times and Calendars

S

spatton

We are using MS Project 2007 SR1

I created a calendar and set the Working Times from 9-12 and 1-4 in an
attempt to leave 2 hours per day to non-project work. The problem
with this scenario is that if we choose a week for work, the actual
days are off because Project trys to account for the 10 hours
"missing" during the week.

I would like to set our Working Times back to 8-12 and 1-5, but when I
go through PWA and then Edit Calendar, I am not finding any place to
change these now.

How can I change working times on a custom calendar?

Thanks

Steve
 
D

Dale Howard [MVP]

spatton --

Log into PWA with administrator permissions. Click Tools - Enterprise
Calendars. Select the Calendar you want to edit and then click the Edit
Calendar button. The system launches Project Professional 2007 and opens
the calendar for editing. Click the Work Weeks tab, select the [Default]
item in the data grid, and then click the Details button. Select Monday
through Friday in the Select Day(s) list and then set your original
schedule. Hope this helps.
 
S

spatton

spatton --

Log into PWA with administrator permissions.  Click Tools - Enterprise
Calendars.  Select the Calendar you want to edit and then click the Edit
Calendar button.  The system launches Project Professional 2007 and opens
the calendar for editing.  Click the Work Weeks tab, select the [Default]
item in the data grid, and then click the Details button.  Select Monday
through Friday in the Select Day(s) list and then set your original
schedule.  Hope this helps.






We are using MS Project 2007 SR1
I created a calendar and set the Working Times from 9-12 and 1-4 in an
attempt to leave 2 hours per day to non-project work.  The problem
with this scenario is that if we choose a week for work, the actual
days are off because Project trys to account for the 10 hours
"missing" during the week.
I would like to set our Working Times back to 8-12 and 1-5, but when I
go through PWA and then Edit Calendar, I am not finding any place to
change these now.
How can I change working times on a custom calendar?

Steve- Hide quoted text -

- Show quoted text -

Thanks - Yes this worked.
 
D

Dale Howard [MVP]

spatton --

You are more than welcome, my friend!




spatton --

Log into PWA with administrator permissions. Click Tools - Enterprise
Calendars. Select the Calendar you want to edit and then click the Edit
Calendar button. The system launches Project Professional 2007 and opens
the calendar for editing. Click the Work Weeks tab, select the [Default]
item in the data grid, and then click the Details button. Select Monday
through Friday in the Select Day(s) list and then set your original
schedule. Hope this helps.






We are using MS Project 2007 SR1
I created a calendar and set the Working Times from 9-12 and 1-4 in an
attempt to leave 2 hours per day to non-project work. The problem
with this scenario is that if we choose a week for work, the actual
days are off because Project trys to account for the 10 hours
"missing" during the week.
I would like to set our Working Times back to 8-12 and 1-5, but when I
go through PWA and then Edit Calendar, I am not finding any place to
change these now.
How can I change working times on a custom calendar?

Steve- Hide quoted text -

- Show quoted text -

Thanks - Yes this worked.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top