S
spatton
We are using MS Project 2007 SR1
I created a calendar and set the Working Times from 9-12 and 1-4 in an
attempt to leave 2 hours per day to non-project work. The problem
with this scenario is that if we choose a week for work, the actual
days are off because Project trys to account for the 10 hours
"missing" during the week.
I would like to set our Working Times back to 8-12 and 1-5, but when I
go through PWA and then Edit Calendar, I am not finding any place to
change these now.
How can I change working times on a custom calendar?
Thanks
Steve
I created a calendar and set the Working Times from 9-12 and 1-4 in an
attempt to leave 2 hours per day to non-project work. The problem
with this scenario is that if we choose a week for work, the actual
days are off because Project trys to account for the 10 hours
"missing" during the week.
I would like to set our Working Times back to 8-12 and 1-5, but when I
go through PWA and then Edit Calendar, I am not finding any place to
change these now.
How can I change working times on a custom calendar?
Thanks
Steve