Hi. I am using Project 2013 Standard and have a very confusing problem.
If I click PROJECT->Change Working Time and look at the "Standard (Project Calendar)" entry I am correctly told it is a base calendar. However, the "Working times" entry for each working day is set to
08:00 to 12:00
i.e. there is no afternoon entry. If I look under the default entry for the working week I can see that each day has set
08:00 to 12:00
13:00 to 17:00
I have tried setting the correct times in each day explicitly (as may be seen in the attached screen shot) and using the project default, but each time I only see the half day shown. If I set a day to "non working time" then it is shown correctly as a non working time day.
Can anybody please help tell me what is going on?
Thanks
Dave
If I click PROJECT->Change Working Time and look at the "Standard (Project Calendar)" entry I am correctly told it is a base calendar. However, the "Working times" entry for each working day is set to
08:00 to 12:00
i.e. there is no afternoon entry. If I look under the default entry for the working week I can see that each day has set
08:00 to 12:00
13:00 to 17:00
I have tried setting the correct times in each day explicitly (as may be seen in the attached screen shot) and using the project default, but each time I only see the half day shown. If I set a day to "non working time" then it is shown correctly as a non working time day.
Can anybody please help tell me what is going on?
Thanks
Dave