P
Patrick Peters
I'm running project 2000. I've got a resource that I have set up as 40%
available (using Max Units on the resource sheet). I assign this resource
to a 40 hr task. Project computes the finish date as if the resource was
100% available to the project. What am I doing wrong? I've tried
levelling, but that doesn't seem to help.
Thanks
Pat
available (using Max Units on the resource sheet). I assign this resource
to a 40 hr task. Project computes the finish date as if the resource was
100% available to the project. What am I doing wrong? I've tried
levelling, but that doesn't seem to help.
Thanks
Pat