V
Vivek S
Hi,
I have a resource that works in multiple projects (A, B and C).
When I open project A in MSProject Professional and view Resource Usage, it
also shows a line item for projects B and C having correct values for "Work".
However when I inculde "Remaining work" column in Resource Usage, it shows
up the same values as "Work" for Projects B and C.
If I open project B also, then it shows the correct value for Remaining work.
Any workaround for it ? Opening all the projects to see correct values for
"reamining work" in resource Usage view is cumbersome.
Thanks
I have a resource that works in multiple projects (A, B and C).
When I open project A in MSProject Professional and view Resource Usage, it
also shows a line item for projects B and C having correct values for "Work".
However when I inculde "Remaining work" column in Resource Usage, it shows
up the same values as "Work" for Projects B and C.
If I open project B also, then it shows the correct value for Remaining work.
Any workaround for it ? Opening all the projects to see correct values for
"reamining work" in resource Usage view is cumbersome.
Thanks