Hi,
In our project planning we have shifted a task from a specific week to a
week later and in the view "resource assignments - timesheet format" we still
see the original planning estimates and the new planning estimates for this
specific task. The project has been published after making the changes.
We make the lines of the scheduled work visible in the view options by
selecting "show scheduled work" via project web access.
In front of the task, column 1, we see the icons indicating that "a task
assignment has been removed". The problem is that in the total number of
hours per day, this "deleted assignment" is still added and apparently taken
into account.
Can anyone help ??
thanks.
Kurt.
In our project planning we have shifted a task from a specific week to a
week later and in the view "resource assignments - timesheet format" we still
see the original planning estimates and the new planning estimates for this
specific task. The project has been published after making the changes.
We make the lines of the scheduled work visible in the view options by
selecting "show scheduled work" via project web access.
In front of the task, column 1, we see the icons indicating that "a task
assignment has been removed". The problem is that in the total number of
hours per day, this "deleted assignment" is still added and apparently taken
into account.
Can anyone help ??
thanks.
Kurt.