U
Ueli
PS07
We made some customizations to the Resource Usage view (two new top level
group 'Project' and 'Resource Type') and show the Cost and the Work column.
Furthermore we only add generic resources and use this view for proposals.
Now we observe a strange behaviour. Sometimes the total cost for a rescource
does not sum up correctly (or does not sum up at all) the costs per task in
the left side table. Strange enough, the totals in the timephased view table
on the right side do show correct values on all levels.
Has anyone observed such behaviour?
Is there a way to force an update/calculation of the values?
Thank you,
Ueli
We made some customizations to the Resource Usage view (two new top level
group 'Project' and 'Resource Type') and show the Cost and the Work column.
Furthermore we only add generic resources and use this view for proposals.
Now we observe a strange behaviour. Sometimes the total cost for a rescource
does not sum up correctly (or does not sum up at all) the costs per task in
the left side table. Strange enough, the totals in the timephased view table
on the right side do show correct values on all levels.
Has anyone observed such behaviour?
Is there a way to force an update/calculation of the values?
Thank you,
Ueli