Mario García
I have installed Project 2000 and I have the following
problem: In summary tasks the calculation of the work
does not consider the allocation of resources to the own
task summarize (but, it does it for the calculation of
the costs). Also, the calculation of working hours for
the global of the project is erroneous (by excess, more
of the double of the real one).
I've installed the SP1 but the problem continues.
Any idea?
List of Sw:
Windows XP Professional
Office 2000
Project 2000