Wrongly calculated working days

R

Remington

Seemed to be a quite simple question but confused me for
sometime.

I'm using Project 2000, for a certain task starting from
Nov 25, ending on Nov 27. The total working days should
be '3'. However, mine always shows '2' working days in
total.

Also would like to know how did it come up with a total
task time like '65.13days, or 14.88days'? Is there any way
to make it without decimals?

Many thanks for answering the freebie's questions
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top