WSSMIGR - "Press enter to continue..." - I don't wont it

M

Massimiliano

Hi guys,
I'm scheduling wssmigr to backup all the share point sites for my project
server. Unfortunately when the activity is complete wssmigr ask for "Press
enter to continue..." ... for this message I can't batch this task 'cause
would remain active some CMD on my system.
Is there anyone that can help me?

Thank you
 
P

Pat

Massimiliano said:
Hi guys,
I'm scheduling wssmigr to backup all the share point sites for my project
server. Unfortunately when the activity is complete wssmigr ask for "Press
enter to continue..." ... for this message I can't batch this task 'cause
would remain active some CMD on my system.
Is there anyone that can help me?

Thank you
Hi Massimiliano,
I replied you in microsoft.public.it.office.project.
 