I am using Project 2003 and exporting all data through the
XML reporting wizard. I want to use the <duration> field,
but am unsure of its format since I typically see values
like PT184H0M0S instead of numbers like "21" days for the
task duration. Please help me make sense of this value.
 
G

Guest

The xxHxMxS format is number of Hours, Minutes, and
Seconds - keeping in mind that the work days are typically
8 hours.
 