Z
Ziebarth
We are starting to look at the end of year planning and want to have a rate
increase in project. There are a number of questions in regards to this
though.
What does the rate change do to a project, not a prorated but a start?
Does it change anything that is not completed by the rate change date or
does it split actuals prior to actuals after, what does it do to tasks that
are % complete instead of actuals?
If you update after the rate change date, can you back date a task to prior
to the rate change date? Has anyone done this, what happened? Is it worth it?
Is there a way to change for just new projects? Ideas, feedback, I would
like it all.
Sorry for all the questions, but if we are going to do this we want to be as
informed as possible.
increase in project. There are a number of questions in regards to this
though.
What does the rate change do to a project, not a prorated but a start?
Does it change anything that is not completed by the rate change date or
does it split actuals prior to actuals after, what does it do to tasks that
are % complete instead of actuals?
If you update after the rate change date, can you back date a task to prior
to the rate change date? Has anyone done this, what happened? Is it worth it?
Is there a way to change for just new projects? Ideas, feedback, I would
like it all.
Sorry for all the questions, but if we are going to do this we want to be as
informed as possible.