C
CF
I have read the posts on grouping resources and found that what I need to do
is either on Project Server or 2007. Having said that I was wondering if
anyone can tell me if there is something I am missing in this resource
grouping workaround that I have for very high level resource tracking
scenario I need to solve.
I know it is not a good idea to assign 2 resources (that signify the same
thing) to a task. But what if our tasks are not effort driven, and I assign
resource UNIX ADMIN 0% and then later resource Bob Bell (who is a Unix admin)
at 5% to task 1.
Then assign resource UNIX ADMIN again at 0% to task 2, and then resource
Jan Thompson (another Unix Admin) at 20%. And so on.
This way I can report how many tasks need UNIX Admins, and at the same time
be able to see if I am over allocating Bob and Jan.
It is very seldom that these tasks are dependent on each other, and the
tasks duration/completion are only tracked once every 2 weeks or once a month.
What am I missing? Potential gotchas?
is either on Project Server or 2007. Having said that I was wondering if
anyone can tell me if there is something I am missing in this resource
grouping workaround that I have for very high level resource tracking
scenario I need to solve.
I know it is not a good idea to assign 2 resources (that signify the same
thing) to a task. But what if our tasks are not effort driven, and I assign
resource UNIX ADMIN 0% and then later resource Bob Bell (who is a Unix admin)
at 5% to task 1.
Then assign resource UNIX ADMIN again at 0% to task 2, and then resource
Jan Thompson (another Unix Admin) at 20%. And so on.
This way I can report how many tasks need UNIX Admins, and at the same time
be able to see if I am over allocating Bob and Jan.
It is very seldom that these tasks are dependent on each other, and the
tasks duration/completion are only tracked once every 2 weeks or once a month.
What am I missing? Potential gotchas?