We are seeing this problem occur frequently. A team member has several tasks
assigned to them and can see the list of tasks in PWA/ Tasks and the next day
or so the tasks dissapear. The message displayed in PWA/Tasks is "you do not
have any tasks assigned to you in any projects".
This has happened to several team members at different times, i have
previously deleted the project and re-published it ant this has resolved the
problem, however I now have team members in multiple projects and I do not
want to have to re-publish projects all the time.
I read one of the posts where it is advised to check the booking type is set
to committed and not proposed, I did check the resource and the booking type
was set to committed.
I'm concerned now, I don't want to have to re-publish all my projects each
time this happens.
Kind regards
Ris
assigned to them and can see the list of tasks in PWA/ Tasks and the next day
or so the tasks dissapear. The message displayed in PWA/Tasks is "you do not
have any tasks assigned to you in any projects".
This has happened to several team members at different times, i have
previously deleted the project and re-published it ant this has resolved the
problem, however I now have team members in multiple projects and I do not
want to have to re-publish projects all the time.
I read one of the posts where it is advised to check the booking type is set
to committed and not proposed, I did check the resource and the booking type
was set to committed.
I'm concerned now, I don't want to have to re-publish all my projects each
time this happens.
Kind regards