J
JoB1
I have team members who zero out remaining hours for tasks that were assigned
to be completed last month (Because the work is complete and no more time is
required.
The PM accepts these updates, but the tasks never disappear from the team
member's PWA task tab.
In MS Proj 2003, the task is shown as 100% complete, it was scheduled for
dates well in the past.
How can I get these tasks to "disintegrate" from the PWA view?
to be completed last month (Because the work is complete and no more time is
required.
The PM accepts these updates, but the tasks never disappear from the team
member's PWA task tab.
In MS Proj 2003, the task is shown as 100% complete, it was scheduled for
dates well in the past.
How can I get these tasks to "disintegrate" from the PWA view?