K
kmbrly
When you change the Work field, a drop-down list will appear with the option
to Decrease/Increase the number of work hours but keeps the task duration the
same. I'm in IT so very few resources have a 100% allocation to one project.
An 8 hour activity may take 2 peopel 4 days.
I'm not about to try to calculate resource % allocations per every task to
eventually come up with the duration AND work hours I need. My scheduling
effort would increase 3 fold.
I've been told that there is a way to change to default so that, when you
update the Work field, it will not recaluculate the Duration field. We can't
figure out how to get that done. Does anyone else know?
to Decrease/Increase the number of work hours but keeps the task duration the
same. I'm in IT so very few resources have a 100% allocation to one project.
An 8 hour activity may take 2 peopel 4 days.
I'm not about to try to calculate resource % allocations per every task to
eventually come up with the duration AND work hours I need. My scheduling
effort would increase 3 fold.
I've been told that there is a way to change to default so that, when you
update the Work field, it will not recaluculate the Duration field. We can't
figure out how to get that done. Does anyone else know?