J
JackD
John Sitka said:JackD I think you may be right but I am in a similar
situation to you as I haven't found anything.
Actually, the situation I described was what I thought your situation was.
My schedule changes slowly and hourly updates would be meaningless. However
I do have a background where we used to have to deal with very expensive
machines.
Concurrency is the most vital part of what I need in terms
of scheduling and capacity planning, I can't stress enough
how important expiditious status updates are. How concurrent?
daily would be fine really but DAILY means once or twice daily
updates of hourly values per task. Unfortunately
the Project product documentation has other focuses but so far I haven't
really seen anything that says the speed of Project or ability
to process that kind of frequency is the deal breaker.
There are warning signs however.
Anyways I'm just trying to mimic our shops process flow.
Barcoding/scanning of operational status has been tried
here and failed miserably. What our people understand and are
disciplined about is going to a website for the stuff they need
and thoughtfully updateing what may be required of them.
I'm trying to find a middle ground. Coding direct Project Updates
would allow customization that could exploit handhelds/our kiosks/
Numeric Controller output, basically anything; but there is even less
information out there about writing such Updates as there is about
setting up Project server. Project Server is a near match to our needs
as far as I can see, but it would require our Project Managers to
develop a flow as far as cycle time is concerned. We could live with that as
long
as the Projects are current to a known point and not a week out of
date.
When I say hourly I mean Joe works 2 hours on TaskA,
5 hours on TaskB, 8 hours on TaskC. in a 10 hour shift.
That makes up his day. Then the afternoon guy comes
in, Repeat.
Both these guys may update their actuals at lunch, after work, the next
morning
etc. upon logical completetion etc. The point is there is a natural flow to
it all
and that flow is, as I have always maintained, the way it really happens.
See Joes 2 hours on TaskA may have a much great significance than 40 hours
spent elsewhere. This 2 hour segment may have been because he completes
just that little bit early so the window of oportuntity presented by that
enables
a cascading effect of MORE optimal decissions to be made when juggling
resources.
It dosen't take much before big gains are made just because we are able to
present
the fact that
Q.
"Hey guess what Joe's done!!!" Isn't that great?"
A.
"Sure is..,glad we found out about it now. We can....!!!"
The superintendent may be asked to help manage a variance in a production
plan.
When this situation comes up the key players or bottlenecks are most likely
known. Mentally; candidate tasks are already being considered as victims for
delay
All these decisions are based on a good knowledge of the MOST asked question
in any custom manufacturing environment.
"How much is left?"...(on that task)
All I want to do is provide a means to get the response to that question
into Project.
Truely the problem is as simple as that. But as of right now a few simple
concepts
or configurations are missing.
I wrote earlier
Well it didn't get said....but Guess what!!!!! there is a page in Project
Server
called Adjust Actuals that provides an interface to apparently do just that.
However mine dosen't seem to be working and that is a very common
issue.(Googled)
Maybe I can figure it out?
So truely I agree with you but I've been looking very hard at the solutions
that are out there and really nothing offers much beyond what Project
does. Be warned hundreds claim that they do.
I find this rather hard to believe. I would think that there must be some
credible production scheduling software out there.
Have you ever devised a VBA Macro that bulk updates from a CSV
Actual Work, Work Remaining?
50 projects in one Master Project. Enterprise Resource Pool
No. I don't use project server on a regular basis.
-Jack